Update Stage 1 Completion Dates

12 September 2025

Moonta Road Project Stage 1 : Updated Completion Dates (Haylock Road to East Terrace)

The Moonta Road upgrade, specifically between Haylock Road and East Terrace, is progressing according to the revised timeline. Below are the updated key milestones and expected completion dates:

  1. Kerbing
    Expected to finish by 30th September 2025
    This stage involves the installation of new kerbs along the stretch of road, which is a crucial step in preparing the road for further works, such as paving and surface treatments.
  2. Final Layer of Rubble & Final Trim
    Expected to finish by 24th October 2025
    The final layer of rubble will be applied, followed by a final trim to ensure the road surface is smooth and even, preparing it for the spray seal application.
  3. Spray Seal & Linemarking
    Scheduled for 27th to 28th October 2025
    During this phase, the road will receive a spray seal coat, followed by linemarking, which will include road markings such as lane dividers and directional arrows to improve traffic flow and safety.
  4. Expected Project Completion
    3rd November 2025
    This will mark the official completion of the Moonta Road Stage 1 project between Haylock Road and East Terrace, assuming all work proceeds as planned.

Note: These dates are subject to potential delays due to unforeseen circumstances, such as the presence of rock, adverse weather conditions, or other project-related setbacks. The project team is working to minimize any disruptions and keep the roadworks on track.