Stage 1 - Haylock Road to East Terrace

14 July 2025

Moonta Road Construction – Stage 1(Haylock Road to East Terrace) has commenced.

  • 20% of the road has been excavated, proof rolled and filled with rubble. Contractors are currently working on installing drainage infrastructure in this stage, before moving onto the next stage of the road.

  • Contractors have encountered rock, this was expected and known through predesign geotechnical investigations. Rock excavation will impact on the delivery timeframes and incur additional costs. Volumes and time delays are recorded and monitored as a variation to the contract. At the time of completing this report these impacts were not quantified.