Office Beach Foreshore Upgrade

15 September 2025

Stage 1 (Office Beach Upgrade) planning has progressed to 70% and includes improved access to the beach and ferry terminal, relocation of the current Office Beach carpark, creation of a foreshore reserve area and a new public toilet facility.

  • Design for the toilet is complete and with an engineering consultant to design footing plans
  • Discussions are underway with a Changing Places accessor to review the plans to progress the conversation to applying for a grant for a changing places facility
  • Additional due diligence is occurring in relation to the relocation of the Office Beach Toilets to the Boat Ramp.
  • Before Stages